Earned value basics

⏱️ 8 min

🎯 Covers these PMP exam tasks: 2.6 Plan and manage finance 2.9 Evaluate project status

Asking "how much have we spent?" isn't enough. You may have spent half the budget, but have you done half the work? Earned value management answers this by comparing three numbers at a given date: planned value (PV), the value of the work that should have been done by now according to the plan; earned value (EV), the value of the work actually done, measured at budgeted rates; and actual cost (AC), what has really been spent. Add to these the budget at completion (BAC), the total budget for the work.

From these we calculate variances. Cost variance: CV = EV − AC; if it's negative, we are over budget. Schedule variance: SV = EV − PV; if it's negative, we are behind schedule. Notice that EV always comes first in both formulas.

Then we calculate indexes, which are easier to compare. Cost performance index: CPI = EV ÷ AC. Schedule performance index: SPI = EV ÷ PV. The rule: above 1 is good (under budget or ahead of schedule), below 1 is bad (over budget or behind), and exactly 1 means right on plan. From the CPI we can forecast the final cost with the simplest formula: estimate at completion EAC = BAC ÷ CPI, assuming current performance continues.

Worked example: a project has BAC = 100,000. After four months the plan called for 40% complete, so PV = 40,000; but only 30% is done, so EV = 30,000; and spending is AC = 36,000. So CV = 30,000 − 36,000 = −6,000 (over budget) and SV = 30,000 − 40,000 = −10,000 (behind). CPI = 30,000 ÷ 36,000 ≈ 0.83, meaning each riyal spent produces only 83 halalas of work, and SPI = 30,000 ÷ 40,000 = 0.75. The forecast is EAC = 100,000 ÷ 0.833 ≈ 120,000.

💡 Key points

  • PV = planned, EV = actually done at budget value, AC = actually spent.
  • CV = EV − AC and SV = EV − PV; negative means trouble.
  • CPI = EV ÷ AC and SPI = EV ÷ PV; above 1 is good, below 1 is bad.
  • EAC = BAC ÷ CPI forecasts the final cost if current performance continues.

🌍 Real-life example

A clinic's mobile app has a budget of 60,000 split into 6 equal screens (10,000 each). Today the plan called for 3 screens (PV = 30,000), and 3 screens are done (EV = 30,000), but 40,000 has been spent. So SPI = 1 (on schedule) but CPI = 30,000 ÷ 40,000 = 0.75, and the forecast cost = 60,000 ÷ 0.75 = 80,000. The schedule looks great while the budget is in danger, something you would miss by watching the deadline alone.

📖 Key terms

Englishالعربية
Earned Value (EV)القيمة المكتسبة
Planned Value (PV)القيمة المخططة
Actual Cost (AC)التكلفة الفعلية
Budget at Completion (BAC)الميزانية عند الإنجاز
Cost / Schedule Performance Index (CPI / SPI)مؤشر أداء التكلفة / الجدول
Estimate at Completion (EAC)التقدير عند الإنجاز

🧠 Check your understanding

Short questions to lock in what you learned. Don't worry, an explanation appears after each answer.

Share "Project Management Basics"

Spread the benefit: a free site to learn project management in English and Arabic, and it works offline on your phone.

Scan with your phone camera to open the site

Install the app on iPhone

  1. Tap the Share button ⬆︎ at the bottom of Safari.
  2. Choose "Add to Home Screen".
  3. Tap "Add".